Asbestos Update: Part 2

I closed the last blog post by sharing that the cost of dealing with all of the asbestos was likely to be in the region of £50,000, and that we have been able to make some progress on reducing that cost.  Now to explain how… Firstly, of the 37 instances of asbestos mentioned previously, 11 of them were within fuse boxes and pipe/boiler gaskets.  These were easily…

Asbestos Update: Part 1

Back in April last year, when I posted the When I Survey… blog entry, we were in the process of having many surveys carried out on the building and the surrounding land, to establish suitability for redevelopment, and to be prepared for any of the surprises that might come up once we do start developing. The most enlightening report from all of those surveys was the…